PARKING RAMP RESTORATION
APPLETON, WISCONSIN
OVERVIEW
Restoration Systems was contracted in the Summer of 2024 to perform emergency repairs to secure and repair a barrier that was struck by a motor vehicle on a parking ramp in Appleton, WI. Restoration Systems Inc. worked with the owner and engineer to design and install a temporary shoring structure to withstand detaching a 27,000 pound precast barrier panel on the fifth story of the structure. Once safely secured and removed, a retrofit cast in place barrier wall was designed and installed with custom made weld clips and anchorages.
SCOPE OF WORK
>> Emergency Shoring
>> Precast Panel Demolition
>> Concrete Repairs
>> Cast-in-Place Barrier Wall
SNAPSHOT
>> Start Date: September 2024
>> Duration: 3 Months
CASE STUDIES
FEATURED PROJECTS
15 BUILDING
Exterior work including facade tuckpointing, brick replacement, and stone patching.
MERCY HEART HOSPITAL
Exterior work, roof repairs, thru-wall flashing, and sealant replacement.
MSP INTERNATIONAL AIRPORT
Repairs to concrete, sealant, and electrical and mechanical systems.
WELLS FARGO
CENTER
Multi-year phased project to install sealant and custom window gaskets.