Restoration Systems Inc. was contracted in Spring of 2020 to perform parking ramp restoration at an office complex in Minneapolis, Minnesota. The parking ramp restoration included post tension cable replacement, post tension cable repairs, structural concrete replacement, installation of a new high-solids polyurethane waterproofing, traffic bearing membrane system for vehicular traffic, asphalt replacement, ceiling and wall painting, and exterior masonry repairs.
SCOPE OF WORK
>> Post Tension Cable Replacement
>> Post Tension Cable Repairs
>> Structural Concrete Replacement
>> Traffic Coating Installation
>> Ceiling and Wall Painting of Parking Structure
>> Parking Stall Striping
>> Asphalt Replacement
>> Exterior Façade Tuckpointing
>> Exterior Brick Replacement
>> Exterior Sealant Replacement
>> Exterior Stone Repairs
>> Exterior Stone Replacement
>> Power Washing Façade Elements
SNAPSHOT
>> Start Date: May 2020
>> Duration: 4 Months
CASE STUDIES
FEATURED PROJECTS
15 BUILDING
Exterior work including facade tuckpointing, brick replacement, and stone patching.
MERCY HEART HOSPITAL
Exterior work, roof repairs, thru-wall flashing, and sealant replacement.
MSP INTERNATIONAL AIRPORT
Repairs to concrete, sealant, and electrical and mechanical systems.
WELLS FARGO
CENTER
Multi-year phased project to install sealant and custom window gaskets.