MINNEAPOLIS
OFFICE COMPLEX

MINNEAPOLIS, MINNESOTA

OVERVIEW

Restoration Systems Inc. was contracted in Spring of 2020 to perform parking ramp restoration at an office complex in Minneapolis, Minnesota. The parking ramp restoration included post tension cable replacement, post tension cable repairs, structural concrete replacement, installation of a new high-solids polyurethane waterproofing, traffic bearing membrane system for vehicular traffic, asphalt replacement, ceiling and wall painting, and exterior masonry repairs.

SCOPE OF WORK

>> Post Tension Cable Replacement

>> Post Tension Cable Repairs

>> Structural Concrete Replacement

>> Traffic Coating Installation

>> Ceiling and Wall Painting of Parking Structure

>> Parking Stall Striping

>> Asphalt Replacement

>> Exterior Façade Tuckpointing

>> Exterior Brick Replacement

>> Exterior Sealant Replacement

>> Exterior Stone Repairs

>> Exterior Stone Replacement

>> Power Washing Façade Elements

SNAPSHOT

>> Start Date: May 2020

>> Duration: 4 Months

CASE STUDIES

RECENT PROJECTS

1ST NATIONAL BANK

Contracted to provide exterior masonry façade restoration repairs.

VIEW PROJECT

WELLS FARGO CENTER

Contracted to perform installation of new custom window gaskets.

VIEW PROJECT

MEARS PARK PLACE APARTMENTS

Contracted to perform plaza restoration.

VIEW PROJECT

800 NICOLLET MALL

Contracted to perform exterior preventative maintenance.

VIEW PROJECT