Project Case Study

Bell Plaza Stair Replacement

A code-compliance retrofit at Bell Plaza in Bloomington, MN. RSI removed a deteriorated metal stairwell, fabricated a new galvanized steel staircase in-house, and installed it on site — restoring safe egress with a system built for Minnesota’s freeze-thaw exposure.

Request a Project Consultation →

Location

Bloomington, MN — Twin Cities Metro

Scope

Metal Fabrication & Stair Replacement

Status

Completed — 1-Month Duration

Context & Scope

Project Overview


A failing exterior staircase at Bell Plaza, replaced in-kind with a new galvanized steel assembly — safe egress restored, code compliance re-established.

Restoration Systems was contracted to remove an existing unsafe metal stairwell at Bell Plaza in Bloomington, Minnesota, within RSI’s Minneapolis service area. The original staircase had deteriorated to a point where continued use posed a safety risk to the building’s staff and the surrounding public.

Working in an active site environment, our crew implemented proper safety measures to protect both occupants and pedestrians during demolition. The existing staircase was removed efficiently and without disruption to the property.

We then fabricated a new galvanized steel staircase in-house and installed it on site, bringing the access point back into compliance with current building code. The completed assembly restored safe egress for the property and replaced a failing component with a system built to withstand Minnesota’s freeze-thaw exposure for the long term.

Deteriorated metal staircase with structural rust failure prior to RSI replacement in Bloomington, MN
The original Bell Plaza staircase prior to demolition — structural rust failure compromising safe egress.
Workers in high-vis vests installing a new galvanized staircase at Bell Plaza, Bloomington, MN
RSI crew installing the new galvanized steel staircase on site after in-house fabrication.
The RSI Approach

Safe. Code-Compliant. Built to Last.


Every RSI project is guided by the same published values — Safety First, Craftsmanship Lasts, and Integrity Is Everything — and the Bell Plaza stair replacement was executed against all three.

Safety-First Demolition

Working in an active site environment, our crew implemented proper safety measures to protect both occupants and pedestrians during demolition. The deteriorated staircase — a clear safety risk to staff and the surrounding public — was removed efficiently and without disruption to the property.

In-House Fabrication

The replacement staircase was fabricated in-house by the RSI team and delivered to site as a complete galvanized steel assembly. Controlling the build under one roof keeps quality, tolerances, and schedule in RSI’s hands from cut to install.

Code-Compliant & Durable

Installation brought the access point back into compliance with current building code and restored safe egress for the property. The galvanized steel specification was chosen to withstand Minnesota’s freeze-thaw exposure for the long term.

On Site

Craftsmanship That Lasts


New code-compliant galvanized stair and guardrail system fabricated and installed by RSI at Bell Plaza, Bloomington, MN
The completed Bell Plaza stair — a new code-compliant galvanized steel staircase and guardrail system, fabricated in-house and installed on site.

The Bell Plaza Stair Replacement is another example of the metal fabrication and structural restoration work RSI delivers for commercial properties across the Twin Cities and greater Minnesota — expert craftsmanship that preserves and protects the places and spaces that fuel the future.

Have a Failing Stair or Metal Assembly?

Founded in 1997 and led by principals averaging more than 25 years of experience, Restoration Systems is the Midwest’s leading restoration company. If your Twin Cities property has a deteriorated exterior stair or structural metal assembly, let’s talk about a code-compliant replacement plan.

Founded 1997 · 25+ Years Experience
LECET Award of Excellence Recipient
EMR Below National Average